Fiber cut has been repaired by construction teams. Datacenter connectivity has been restored.
Identified
Update
Update: Construction teams are still en-route to the source of the fiber cut.
Identified
Identified
Update: Construction crews have been dispatched to replace the cut fiber. I should have another update in 30-40 minutes.
Investigating
Investigating
Segra is reporting a fiber cut on one of the main backbones that occurred at 12:10 AM. Techs are on site investigating the damage. The facility has not provided an estimated time to restore.